- Completed Projects
- Deniliquin Golf Club Water Efficiency Project
- Mokoan Project - Victoria
- Channel Automation Central Goulburn Irrigation District - Victoria
- Improved Flow Measurement - Goulburn River Irrigation Areas, VIC
- Hay Private Irrigation District (PID) Pressurised Stock and Domestic Scheme, NSW
- Water Entitlement Purchase
- Edward River Wetlands, NSW
- Coleambally Irrigation Area, NSW - Channel Automation
- Woorinen Pipeline - Pressurised Horticultural Irrigation Supply System - Victoria
- Normanville Pipeline Project - Victoria
- Improved Measurement of Small Volume Supplies in Irrigation Districts (IMSVSID) - Victoria
- Alternate Water Supply - Forest Creek, NSW Stage 1
- Alternative Water Supply - Forest Creek, NSW Stage 2
- Barren Box Swamp - NSW
- Current Projects
Coleambally Irrigation Area, NSW - Channel Automation
Water Saved 3,500 ML (3.5 GL)
CICL Conveyance Entitlement
This new technology automated the operation of regulating structures and has saved water through reduced over supply and weir pool spills. Operationally these spills typically flow into drains where water had been previously used by opportunistic licenced diverters or evaporated before it reached a regulated water course.
The savings will accrue through the subdivision of Coleambally Irrigation Cooperative Limited's conveyance licence.
This project has:
- Achieved 3.5 gigalitres in water savings which can be returned to the river system for use in environmental flows
- Improved service levels to irrigators along the southern portion of the Coleambally Irrigation area